Project

Innovation & Efficiency: Asphalt Conveyer

On the eastern end of the project, 91¸£Àûµ¼º½ engineered a unique asphalt conveyor to help streamline hauling processes for crews.

The solution helped move asphalt safely from the plant, over the highway, and into a hopper in the median-area work zone. From there, dump trucks were able to transport the asphalt to onsite paving equipment – without having to go through traffic and slow the traveling public.

The conveyor helped save an additional 8,000 loads from being hauled, preventing dump trucks from needing to merge in and out of traffic while working.

The conveyer also reduced the total number of trucks and fuel needed to run the project. A single truck only has to drive around 100 yards to move the asphalt from the plant to the conveyer. Compare this to a 20-mile round trip that might be required without the conveyer.

Scheduling: Two Diverging Diamond Interchanges

While original project plans only called for one DDI, the NCDOT added a second Diverging Diamond Interchange for the I-40 project.

A DDI allows two directions of traffic – guided by traffic signals, pavement markings and concrete barriers – to cross over each other at traffic signals. This design allows drivers to come through an intersection more smoothly and safely.

To accommodate the DDI in the 40/42 area, two new bridges were built and the roads and area around both sides of the bridge were expanded.

NCDOT added a second DDI to address traffic concerns where Jones Sausage Road crosses over the interstate. This DDI was built on the existing bridge, which is not typical and required a retrofit.

Crews had to pave the first lift of surface then adjust and activate new signals for the pattern over a single weekend. Once in this pattern, 91¸£Àûµ¼º½ successfully met the 28-day timeline to complete the median barrier and islands and open the full pattern.

Strategy: Safety & Traffic Solutions

Traffic is always a top concern. It impacts not only the traveling p